Knotweed removal dig and cap contract
By The JKL Team

Knotweed removal dig and cap contract

PROJECT EXAMPLE: Enabling commercial development 

A commercial reduced level dig and cap contract to remove Japanese knotweed growing adjacent to a rail network and river.

Japanese knotweed growing through a metal barrier

THE SITE

A survey identified Japanese knotweed within an area of proposed landscaping on this site. We proposed excavation to a reduced level and the remaining knotweed contaminated ground capped with a specialist horizontal root barrier. There were several key considerations with this site.

KEY CONSIDERATIONS

Railway tracks

WORKING NEAR RAILWAY LAND

Excavations near railway land required necessary checks and agreements with Network Rail to gain approval for excavations to the boundary with their land.

Metal fencing around a knotweed area

BIO-SECURITY RISK SITE

The knotweed areas had been heavily disturbed during recent works (and historically around 2021 when the total site was levelled and graded) meaning the knotweed had been translocated around the site.

A Japanese knotweed crown

WORKING WITH DISTURBED GROUND

This site possessed made ground, which could result in significantly greater lateral or vertical spread of underground plant propagules (such as knotweed rhizome) than found in virgin/normal ground conditions. Plants spread furthest where the ground provides least resistance.

CONTRACT DELIVERY

We carried out reduced level excavation of the knotweed areas according to the client’s formation depths, with all waste transferred across site via a dumper and loaded directly into a RoRo skip for removed to landfill.

Excavator removing soil from knotweed site

 

Rail fencing barrier blocking off excavation area

A specialist root barrier laid on excavated ground

A specialist root barrier was laid horizontally and then returned vertically to the boundary. The void was partially backfilled to secure the barrier.

Wooden fencing panels

The main developer did not want the root barrier to be fixed to the site boundaries (the TFL fence) so instead the barrier was laid against it. The client’s final hard landscaping to the area would sufficiently hold the barrier against the boundary.

THE OUTCOME

With the root barrier installed, all waste was taken to a licensed landfill site. We factored into the contract twice yearly monitoring of the whole site for any occurrences of Japanese knotweed.

0333 2414 413

Contents